US Data Center Construction Costs Surge 13%. AI Boom Pushes Prices Up 3 Times Faster Than Normal.
America’s artificial intelligence infrastructure boom is becoming increasingly expensive as developers compete for limited electricity supplies, skilled workers, and construction materials needed to build data centers.
U.S. data center construction costs increased 13% year over year in 2026, more than twice the global rate, according to a new report from global project management company Turner & Townsend.
The increase was approximately three times the average annual rate recorded over the past decade, highlighting the unprecedented pressure that AI investment is placing on the construction industry.
The report analyzed more than 500 active or recently completed projects across 62 global markets and surveyed 400 data center industry experts. While construction cost inflation showed some signs of stabilization, the growing demand for computing capacity and increasingly aggressive development schedules continued to drive expenses higher.
Technology companies are racing to expand their infrastructure to accommodate increasingly sophisticated AI models, placing additional pressure on contractors responsible for delivering large-scale projects within compressed timelines.
Paul Barry, North America data center lead at Turner & Townsend, explained that contractors are incorporating additional financial protections into their pricing to account for accelerated construction schedules. “More aggressive schedules tie to contractors in particular and subcontractors baking in more risk allowances in their pricing,” Barry said.
These additional expenses include overtime pay, incentives to attract workers and higher fees associated with accepting the risks of completing projects faster than usual. The rising costs come as investment in digital infrastructure is expected to expand substantially over the coming decades.
A recent PwC report projected that annual global data center capital expenditures will increase from approximately $800 billion in 2026 to $1.8 trillion by 2050. The United States is expected to attract almost half of global investment in AI infrastructure, including data centers and semiconductor chips.
However, securing sufficient electricity remains one of the greatest challenges facing developers. Approximately 56% of industry professionals surveyed by Turner & Townsend identified power availability as a major obstacle to delivering data center projects.
More than half said securing utility connections typically takes between one and two years, while nearly one-third reported waiting periods exceeding two years. These delays threaten to complicate expansion plans for technology companies that need additional computing capacity to support their AI products and services.
Construction costs also vary considerably across regional markets. Based on a typical 60-megawatt data center design, construction costs reached $15.01 per watt in Silicon Valley, compared with $10.51 per watt in Dallas.
Labor availability presents another significant obstacle, as data center construction requires specialized workers capable of installing complex electrical, mechanical, and cooling systems, creating competition for skilled professionals. Only slightly more than one-quarter of survey respondents said contractors had sufficient capacity to manage their construction backlogs.
The shortage is particularly challenging as multiple developers pursue large infrastructure projects simultaneously, increasing competition for workers and contributing to higher labor expenses. Despite the sharp increase in construction costs this year, Turner & Townsend expects inflation to moderate somewhat in 2027.
Barry anticipates U.S. data center construction costs will increase between 6% and 10% next year, partly because many major developments have already secured contracts that incorporate financial allowances for construction risks.
However, continued growth in AI infrastructure demand could sustain pressure on the construction sector, particularly if electricity availability and workforce constraints persist. “I think we’ve hit a big surge in 2026, especially of new big major projects that have been procured,” Barry said.